Rebuilding the Spencerville Seventh-day Adventist Church

Rebuilding the Spencerville Seventh-day Adventist Church

Project Knowledgebase

Public view Committee sign in

Project Timeline

From the fire in August 2024 through the current design and permitting work. Filter by phase to focus on one chapter of the project.

Reset
Design & Planning
Upcoming

3D renderings and work-group validation

Two-dimensional plans will be developed into three-dimensional renderings; work groups will be invited to validate the finer details.

Upcoming Public
2026

Master campus plan and initial space plan produced

Built around a square footage thoughtfully sized to serve the congregation well into the future, covering sanctuary, fellowship hall, Sabbath School rooms, and administrative offices.

Completed Public
2026

Organ replacement evaluation

An advisory group of craftsmen and musicians is evaluating two paths: restoring a used instrument or commissioning a new one.

In progress Public
Apr–May 2026

Soil boring analysis

Assessed whether architectural plans align with the geotechnical conditions and realities of the property.

Completed Public
Mar 2026

Civil engineering plans finalized

GLW finalized soil grading plans, preliminary stormwater management areas, and a forest conservation plan in line with county requirements.

Completed Public
Early 2026

Design work groups formed and heard

Work groups covering music, media, acoustics, children's ministries, youth and young adult Sabbath School, and hospitality reported to the Committee. The architects devoted an entire day to listening to their needs.

Completed Public
Oct 6, 2025

Architect-led visioning meetings

The Intec Group led intentional visioning sessions drawing out congregational preferences for look and feel, aesthetic and function, and which design approach best fits Spencerville.

Completed Public
Fundraising
Upcoming

Fundraising campaign structure

A dedicated team has been formed and is beginning to structure the approach for meeting the fundraising goal together.

Upcoming Public
Permitting
Aug 2026

Preliminary plan submission to Montgomery County

A substantial milestone bundling soil erosion control, forest conservation, geothermal, traffic control, fire access, and sewage plans — all required for county approval to move forward.

Upcoming Public
Fall 2025

County permitting requirements satisfied

Montgomery County's process is rigorous; many months of diligent effort were required, including an approved sediment and erosion control plan.

Completed Public
Demolition
Jun–Jul 2026

Soil stabilization / grass establishment

The county requires grass grown over the demolished footprint to recognize demolition as complete. Led by Head Deacon Tom Henkel with volunteers. Conditions are challenging but grass has started to grow. This is the final step to close out demolition.

In progress Public
Feb 2026

Demolition concludes

Structure removal complete. County close-out still requires successful soil stabilization.

Completed Public
Jan 30, 2026

Demolition begins

The team made quick work of the project, concluding in February.

Completed Public
Jan 16, 2026

Demolition permit approved

Approval from Montgomery County cleared the way for demolition to begin.

Completed Public
Summer/Fall 2025

Pre-demolition preparatory work

Removal of the septic system, asbestos abatement, and disconnection of all utility service to the property.

Completed Public
Partner Selection
Summer 2025

The Intec Group selected as architect of record

Committee representatives reviewed architectural proposals from a vetted list of firms before selecting Intec.

Completed Public
Summer 2025

Civil engineering, land use attorney, permit expeditor, and pre-con firm engaged

Each vendor selected only after the committee vetted and weighed multiple strong options, with assistance from the project management firm.

Completed Public
Spring 2025

Project management firm engaged

The first and most essential partner, bringing experience with large commercial projects and deep familiarity with Montgomery County.

Completed Public
Spring 2025

Demolition firm selected

Selected next, since the previous structure had to be safely taken down before anything new could rise.

Completed Public
Congregational Input
Mar 2025

Congregational survey administered

Input grew into a comprehensive vision for the entire 38-acre property — not only a new church structure, but walking trails and a potential new home for Spencerville Adventist Academy.

Completed Public
Feb 2025

Congregational survey developed

One of the Committee's first acts was to hear directly from members about what future facilities and ministries should become.

Completed Public
Governance & Structure
Late fall 2024

Building Committee named and elected

The Church Board drew together stakeholders and subject-matter experts from within the congregation.

Completed Public
Late fall 2024

Terms of Reference defined

The Church Board clarified the Committee's authority and how it relates to the Church Board and the wider membership.

Completed Public
Late fall 2024

Strategic direction established

Themes and goals that now anchor every decision, keeping the project aligned to mission, vision, and goals at each step.

Completed Public
Immediate Aftermath
Late summer 2024

Investigation, salvage, and member walkthrough

Worked with county officials on the cause investigation, opened dialogue with county departments about the future structure, salvaged preservable items, and organized a walkthrough so members could survey the damage and begin to grieve together.

Completed Public
Aug 9, 2024

Fire destroys the church building

The fire that took the church home. The congregation began meeting off-site, currently at The Lutheran Church of St. Andrew.

Completed Public